Projects

Greater Colombo Wastewater Management Project

 GREATER COLOMBO WASTEWATER MANAGEMENT PROJECT

  • Client: National Water Supply and Drainage Board
  • Date of commencement: January 16, 2015
  • Date of completion: February 28, 2017
The scope of the project included rehabilitation of four wastewater pump stations under Kolonnawa Sewerage System and two pump stations of Dehiwala and Mt. Lavinia Sewerage System. The project rehabilitated above pump stations with fitted SCADA systems which automated the operation process by allowing operators and facility personnel to monitor and control the equipment either locally or remotely.