Buildings
Development of a Logistics Park at Kimbulapitiya
- Client: WUS Logistics Private Limited
- Date of commencement: October 01, 2019
- Date of completion: October 31, 2021
This project includes the design and construction of a warehouse facility and other associated facilities of the logistics park.
The 42-acre logistics park includes a 4.6 MVA CEB connection, site offices, workshops, staff quarters, storm water drainage with retention ponds, and all ancillary services required to support both the operation of the Camso Loadstar Distribution Centre and the additional plots available at site. The additional plots, which amount to almost 1,000,000 sq. ft. of warehousing space to be developed, have been finished with underground electricity and water supply termination points, additional MEP service ducts for fibre optics etc, perimeter drainage, and have clear access via an A grade, 17 m wide internal road network.